Park Royal Regency Heights
Metres of Pipework
Homes
Week Programme
PROJECT DETAILS
OVERVIEW:
The site is part of major regeneration master plan of Park Royal area which will cover over 25,000 homes and two new railway stations, part of two major projects (HS2 and Crossrail).
CLIENT:
Pinnacle Power
VALUE:
£500K
PROGRAMME:
Feb 2019 to Jun 2019
CHALLENGES & SOLUTIONS
Installation of 350m dual Kingspan LOGSTOR pipe in 700m trench with depth between 1.7 to 3.5m deep.
Worked alongside and co-ordinating with other contractors under the same master plan, using daily and weekly coordination meetings.
Implementing engineering solution to connect onto a live network, via pipe freezing and line stopping of 600mm diameter twin spine.
Liaison with local authority and stakeholders to enable road works and facilitate installation of 3 new connections into the developments.